#81 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 24 August 2023 - 10:06 PM

Sound Transit Board approves Spring 2024 opening for eight 2 Line stations

 

New Eastside Link service will launch between Bellevue and Redmond

 
August 24, 2023

 

Sound Transit today announced that the Link 2 Line can begin operating passenger service between South Bellevue and Redmond Technology stations in Spring 2024. The Sound Transit Board approved opening the eight-station segment for service prior to completion of the full East Link Extension. 

 

Service on the 2 Line is proposed to run with two-car trains every 10 minutes, 16 hours a day. The final service level will be approved by the Sound Transit Board as part of the 2024 Service Plan. This action is expected in October. 

 

This initial 2 Line service will offer Eastside passengers reliable, traffic-free trips between South Bellevue and Redmond Technology stations. Service will also connect passengers to Overlake Medical Center, the Spring District and the BelRed area.

 

The Board’s action included provisions to meet ridership demand on the 1 Line, including maximizing peak-hour service, adding bus service in Snohomish County and support for Lynnwood passengers until the opening of the full East Link Extension.

 

“It’s an exciting step to connect more communities via fast, carbon-free Link light rail, and opening these stations on the Eastside is the opening act of the 2 Line,” said Sound Transit Board Chair and King County Executive Dow Constantine. “From Redmond to Bellevue, people have a new option to get to work, school, and all the things that make this community special, and I’m excited to see what’s next when the 2 Line crosses Lake Washington in 2025.”

 

Sound Transit is working with regional transit partners on plans to coordinate the 2 Line opening closely with other spring service changes on ST Express, King County Metro Transit, and Community Transit bus routes. This coordination will support ongoing regional mobility connectivity for riders across all regional transit modes and services.

 

Existing ST Express and King County Metro routes including Route 550, B Line, and other local routes are anticipated to continue operating on their current routes until the full 2 Line opens in 2025.

 

“Almost exactly one year ago, when we first learned that Eastlink light rail would be significantly delayed due to workmanship issues on the I-90 bridge, I proposed that we open an Eastside-only starter line. Today, I was pleased that the Board unanimously decided to approve this plan,” said Sound Transit Board Member and King County Council Member Claudia Balducci “This pivot from a long-established plan to adapt to changing circumstances is a testament to hard work, creativity and nimble action by agency staff, as well as the overwhelming enthusiasm by cities and community members from across the Eastside who know how transformational these generational transit opportunities will be and how important it is to open them ASAP.” 

 

“The City of Bellevue and Sound Transit have partnered on a multimodal future for many years, and today’s outcome marks a significant step in realizing our shared vision for mobility on the Eastside. We are thrilled that new light rail service will launch this spring, connecting people in Bellevue to their jobs and destinations,” said Bellevue Mayor Lynne Robinson.

 

“I applaud Sound Transit’s commitment to bring light rail to the Eastside next year through this creative approach,” said Redmond Mayor Angela Birney. “Increasing both connectivity and reliability with additional transportation options, the East Link starter line will improve access for our community and make a positive impact throughout the region.”

 

This incredible accomplishment required significant commitment and collaboration across the entire Sound Transit Team, with King County Metro who hires for and operates our service, and by our federal, state, and local partners for every required review and approval,” said Sound Transit CEO Julie Timm. “It was seriously hard work to assess and then remove the barriers to accelerate opening of light rail on the Eastside by Spring 2024, and there were many moments where it looked like this would be an impossible task in the time available to us. I am proud of the team’s unwavering dedication as Sound Transit continues to make history with the opening of each extension connecting the region through the largest transit expansion program in the country.”

 

Voters approved the East Link Extension in 2008 as part of the Sound Transit 2 ballot measure. Construction on the project began in 2017, including sequential excavation mining of the one-half-mile Bellevue tunnel, which was completed in 2020. Light rail test trains have been operating across the alignment to test the overhead electrical power system and train signal system, and simulated service is expected to begin in early 2024.

 

The Sound Transit Board authorized up to $43 million from the existing East Link Extension $3.68 billion budget to fund the activities necessary to open the East Link Starter Line in Spring 2024.

 

 



#82 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 24 August 2023 - 10:27 PM

The Seattle (WA) Times, 8/24/23

 
Eastside-only light rail should open in March, Sound Transit says

 

Like much of the public, Sound Transit leaders are sick of watching tracks and stations sit unused in Bellevue and Redmond. So, they are aiming to open an Eastside-only starter line in March.

 

Trains will make eight stops between Redmond Technology Station, which adjoins the Microsoft campus, and South Bellevue Station, which is equipped with a new 1,500-stall park-and-ride garage.

 

This will be the start of light-rail service on the Eastside, arriving as Sound Transit’s full extension there is burdened by massive construction delays in the former express lanes of Interstate 90, where trains won’t cross Lake Washington between Bellevue, Mercer Island and Seattle’s International District/Chinatown Station until 2025.

 

 

Continue here.  



#83 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82319 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 07 September 2023 - 06:07 PM

Seattle Transit Blog,  9/6/23:

 


 

   Breaking down East Link Starter Line ridership  

 

 

Now that Sound Transit has paved the way for an East Link Starter Line (ELSL) opening for next Spring, it’s worth deep diving into the projected ridership numbers. At the last Sound Transit Board meeting, early ridership estimates were pegged at a modest 6,000 average weekday boardings, reflecting limited demand until the 2-Line is fully connected to the main 1-Line spine via I-90.

 

Blog

 

The name that will apply for the limited time the 2 line is not connected to the 1 line will be ELSL (East Link Starter Line).



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#84 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82319 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 20 September 2023 - 10:07 PM

Not so fast..... why not have another reason to delay things even further???

 

KIRO-TV, Channel 7 in Seattle, WA, 9/20/23:

 


 

    Bellevue’s light rail set to open in spring already having problems 

 

 

Bellevue’s light rail line isn’t supposed to open until the spring but something’s already broken.

 

Full story



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#85 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 31 October 2023 - 09:23 PM

Sound Transit news release

 

Pre-revenue testing begins Nov. 1 on East Link   
 
Trains will be traveling frequently throughout the day and night, including at street crossings
 
October 31, 2023

 

Testing on the 2 Line is entering the pre-revenue phase starting Wednesday, Nov. 1. This phase includes training for operators and maintenance staff, and continued testing to ensure stations, tracks, utilities, and vehicles work together as expected in preparation for the start of service next spring. 

 

Light rail vehicles will run frequently between the South Bellevue and Redmond Technology stations, including at street crossings in the Bel-Red area. Pedestrians and motorists should be alert for trains and expect they could be running at any time of the day or night.

 

Here are tips for staying safe at rail crossings:

  • Look both ways. Trains come from both directions.
  • Stay alert at crossings by removing headphones and putting screens down.
  • Always use crosswalks and pay attention to crossing signals. Trains always have the right of way.
  • When riding a bike, always cross tracks at a 90-degree angle to prevent wheels from getting stuck.

 

In addition to trains on the tracks, people can expect to see maintenance vehicles, testing equipment, and personnel involved in the testing process, and hear sounds typical in an operating light rail system including station announcements, wheels on the tracks, and warning signals.

 

The next phase of testing will be simulated service, expected to begin early next year.

 

Learn more about the 2 Line at soundtransit.org/blog/platform/get-ready-new-link-service-eastside-next-spring

 

 



#86 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82319 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 24 January 2024 - 06:30 PM

City of Bellevue, WA site, 1/24/24:
 

 

  Simulated light rail service through Bellevue starts   

 

 

In preparation for the launch of the Eastside light rail starter line this spring, Sound Transit will start sending trains on regular practice runs every 10 to 15 minutes between the South Bellevue and Redmond Technology stations, starting this week.

 

Read



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#87 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82319 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 04 February 2024 - 02:45 PM

KOMO-TV, Channel 4 in Seattle, WA, 2/4/24:

 


 

  Final testing underway as Eastside Link light rail prepares for spring launch      

 

 

Keeping plans on track to get Sound Transit trains running on the Eastside means getting those trains on the track.

 

Continue reading



Kevin Korell


OTOL Board Leader


Lakewood, NJ