HART awards construction contract for Waipahu train stations


  • Please log in to reply
2 replies to this topic

#1 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82315 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 10 March 2015 - 11:39 AM

Progressive Railroading, 3/10/15:

 


Bids for three Honolulu rail stations come in higher than estimates

 

Five companies submitted higher-than expected bids last week to the Honolulu Authority for Rapid Transportation (HART) for a project to build three stations as part of the city's plan to build a 20-mile elevated light-rail line.

 

The story



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#2 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 11 June 2015 - 08:48 AM

HART news release, 6/10:

 

HART awards construction contract for Waipahu train stations

 

HART today awarded a construction contract to Hawaiian Dredging Construction Company to build three rail stations in the Waipahu area. 

 

Hawaiian Dredging Construction Company received a $78.9 million contract for the Farrington Highway station group, consisting of the West Loch, Waipahu Transit Center and Leeward Community College stations.

 

Bids for the station group contract were opened in March. Hawaiian Dredging Construction Company was the apparent low bidder. The second-lowest bidder filed a bid protest that was denied by HART. That company then filed an appeal in April with the state Department of Commerce and Consumer Affairs (DCCA). The DCCA ruled in HART’s favor on May 28. These challenges delayed the award by about three months.

 

The original nine-station contract was broken into three smaller contract packages to encourage broader participation by contractors during the bidding process and create more competitive prices.

 

Contract bids for the West Oahu station group, consisting of the East Kapolei, UHWest Oahu and Hoopili stations, will be opened at HART’s offices, 1099 Alakea Street, at 2 p.m. Tuesday, June 16.

 

A request for contract bids for the Kamehameha Highway station group, which includes the Pearl Highlands, Pearlridge and Aloha Stadium stations, will be issued in August.



#3 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 24 June 2017 - 06:06 AM

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

HART WEEKLY eBLAST  | June 23, 2017

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

PEDESTRIAN BRIDGE IN WAIPAHU

af826eea-b45d-41f8-b1ee-caab15fd8509.jpg

This was the scene last Friday night, June 16, on the makai side of Farrington Highway near the intersection at Leoku Street.  

 

Hawaii Dredging Construction Company crews lifted the 197,000 pound pedestrian bridge into position at the future home of HART's West Loch Station.  

6aa46d4c-61f3-4f23-b1fa-56dad4951eda.jpg
 

The mauka side bridge was installed earlier this month.  

 

Rail station construction continues between Aloha Stadium and Kapolei.