Posted 28 August 2017 - 11:51 PM

Skift, 8/28/17:

 


 

 

Hawaii’s $9.5 Billion Commuter Rail Project May Never Be Finished

 

 

Train tracks supported by concrete pillars snake through Oahu neighborhoods and across its lush scenery, ending abruptly in an empty, overgrown field. They’re part of a planned $9.5 billion rail transit project – one of the most expensive per capita in the United States.

 

This one



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#22 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 15 September 2017 - 07:13 PM

Excerpt:

 

 

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

 

HART WEEKLY eBLAST  | September 15, 2017

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

 

 

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

READ THE LATEST PROGRESS REPORT ON THE HONOLULU RAIL PROJECT

26386a54-d57e-4526-89ac-eb7594fba1fb.jpg
 

Each month, the HART Board of Directors is presented with a comprehensive report on the current status of the rail project.  The Honolulu Authority for Rapid Transportation believes it is essential to keep the public up-to-date on the project. Therefore, each monthly report is open for public review.  

 

Please click here to review the latest report.

 

 

 

   
 



#23 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 05 October 2017 - 08:40 AM

HART - published 10/2/17

 

 



#24 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 20 October 2017 - 08:35 PM

Excerpt:

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

HART WEEKLY eBLAST  | October 20, 2017

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

219e47bb-6cec-4591-877f-430f66d114e4.jpg
 

READ THE LATEST PROGRESS REPORT ON THE HONOLULU RAIL PROJECT!

 

e068d7d0-3861-4bf3-ade9-eaf4c9daca76.png  
 

Each month, the HART Board of Directors is presented with a comprehensive report on the current status of the rail project.  The Honolulu Authority for Rapid Transportation believes it is essential to keep the public up-to-date on the project. Therefore, each monthly report is open for public review.  

 

Please click here to review the latest report.

 



#25 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 30 December 2017 - 11:44 AM

Excerpt:

 

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

HART WEEKLY eBLAST  | December 29, 2017

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

219e47bb-6cec-4591-877f-430f66d114e4.jpg
 

 

 

 

READ THE LATEST PROGRESS REPORT ON THE HONOLULU RAIL TRANSIT PROJECT!

 

Each month, the HART Board of Directors receives a comprehensive report on the current status of the rail project.  The Honolulu Authority for Rapid Transportation believes it is essential to keep the public up-to-date on the project. Therefore, each monthly report is open for public review.  

 

Click here to review the latest report.

 



#26 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 11 January 2018 - 01:54 PM

Honolulu Transit, 12/20/17
 

Construction Progress Video - December 2017

 

View the Video of the Honolulu rail construction project from East Kapolei to the Honolulu International Airport

 



#27 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 07 February 2018 - 10:48 AM

HART email 2/6/18:

 

HART's Photo(s) of the Week!

 

81fbff42-0f04-4996-80fd-d780c0f8d872.jpg

 

  

Rail Project Celebrates Milestone!

    

The Honolulu Rail Project features four distinct guideway sections: the Farrington Highway Section (East Kapolei to Pearl Highlands), the Kamehameha Highway Section (from Pearl City to Aloha Stadium), the Airport Guideway (from Aloha Stadium to Middle Street), and the City Center Guideway (from Middle Street into Ala Moana).  While the first two phases of guideway work are about 99-percent complete, the Airport Guideway is hitting full stride and is even slightly ahead of schedule.

 

 

S.gif

8388eafb-00dd-4ea4-9d21-061a21bb776d.jpg

 

 

Work on the Airport Guideway reached a milestone this week with the installation of the section's first support columns.  HART and contractor Shimmick/Traylor/Granite Joint Venture spent the past few weeks drilling foundations for the guideway's support columns and recently began erecting the first set of piers that will support the 5.15-mile long section.  In our photo of the week, crews pour concrete to build the support piers  that will range from 24 to 71 feet high and have foundations that can be as much as 300 feet deep.  

 

5a9e8372-8a25-4f3b-abef-c3fb298bcc05.jpg

 
 

 



#28 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 20 July 2018 - 05:44 PM

Excerpt:

 

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

HART WEEKLY eNEWS

July 20, 2018

 

 

 

 

97d7279d-b9dc-4929-a283-91b4f161b6d3.jpg

READ THE LATEST PROGRESS REPORT ON THE HONOLULU RAIL TRANSIT PROJECT!

 

Each month, the HART Board of Directors receives a comprehensive report on the current status of the rail project.  The Honolulu Authority for Rapid Transportation believes it is essential to be transparent and keep the public up-to-date on the project. Therefore, each monthly report is posted for public review.

 

Click here to review the latest report

 

 

 

 

 

 

 

 

 

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

219e47bb-6cec-4591-877f-430f66d114e4.jpg

CHECK OUT HART's LATEST CONSTRUCTION VIDEO!

 

 



#29 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 19 January 2019 - 07:19 AM

Excerpt:

HART WEEKLY eNEWS

January 18, 2019

 

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

219e47bb-6cec-4591-877f-430f66d114e4.jpg

\READ THE LATEST PROGRESS REPORT ON THE HONOLULU RAIL TRANSIT PROJECT

 

27ae3760-ad3f-41fd-8cea-ccf10a9fe191.png

 

Each month, the HART Board of Directors receives a comprehensive report on the current status of the rail project.  The Honolulu Authority for Rapid Transportation believes it is essential to be transparent and keep the public up-to-date on the project. Therefore, each monthly report is posted for public review.

 

 Click here to review the report

  

Click here to review the report's highlights

 



#30 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43492 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 21 April 2019 - 04:26 PM

Excerpt:

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

HART WEEKLY eNEWS

April 12, 2019

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

CHECK OUT OUR LATEST CONSTRUCTION PROGRESS VIDEO!

 

The Honolulu Authority for Rapid Transportation recently put out its latest construction progress video, encompassing active construction from January through March of this year.

 

Check out the video here:

 

 Construction Progress Video - March 2019

 