Jump to content


Photo

HART Live Train and Energized Track Testing


  • Please log in to reply
5 replies to this topic

#1 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 01 September 2017 - 07:38 PM

Excerpt:

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

 

 

HART WEEKLY eBLAST  | September 1, 2017

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

 

 219e47bb-6cec-4591-877f-430f66d114e4.jpg

HONOLULU'S RAIL TRANSIT PROJECT SET TO BEGIN LIVE TRAIN AND ENERGIZED 

TRACK TESTING

 

a0eb9e46-f87e-42f7-9363-858afda4f8f1.jpg

FOR THE FIRST TIME EVER, RAIL CARS WILL

OPERATE UNDER THEIR OWN POWER

 

The Honolulu Authority for Rapid Transportation (HART) and its contractor Ansaldo Hawaii Joint Venture will soon be conducting live testing of its first rail cars.  As part of the process, engineers will also be energizing the contact rail or so called "third-rail" used as the rail cars' power source.

 

7b7c4307-64a0-4569-b39a-a02a307d4c1f.jpg

This will mark the first time that trains will operate on the guideway under their own power.  For testing purposes, trains will have operators on-board however when operational, the trains will be fully-automated and driver-less.

 

All testing will be done within restricted zones for the safety of the public and contractors.  As testing expands, more guideway segments will be brought online.

 

bec3181b-1607-4063-9cb6-428ebc5e7158.jpg

Train testing will examine the acceleration and operational abilities of the rail cars under varying load conditions and at speeds of up to 55 miles per hour.  Braking tests will also be conducted.

 

HART is working to raise public awareness about the dynamic section electrification and train testing. As testing begins and certainly moving forward, HART reminds the public that all rail tracks should be considered live and dangerous.  Any contact with all rail tracks is to be avoided.

 

Testing dates of note:

  • Tuesday, September 5 - Waipahu Traction Power Sub-Station short circuit test
  • Wednesday, September 6 - Initial energization of third rail in testing section
  • Late September - Early October - Rail cars testing on energized track

Important Notes

  • There is to be absolutely no access to the testing section
  • Always consider all rail tracks as LIVE at ALL TIMES
  • Respect all safety signage installed in test areas
  • No stepping or sitting on 3rd rail cover boards
  • No placing of conductive materials on or near the 3rd rail


#2 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 15 October 2017 - 09:10 AM

Excerpt:

 

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

HART WEEKLY eBLAST  | October 13, 2017

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

 

 

 

 219e47bb-6cec-4591-877f-430f66d114e4.jpg

GETTING READY TO ROLL!

 

4cd96a7f-12ca-4921-81fa-c87198c143ee.jpg
 

In preparation for fully self-powered testing, HART engineers rolled one of the Rail Project's trains out onto the guideway recently. The roll-out was successful, clearing the way for trains to run autonomously during full testing in the near future!

 

We'll keep you posted as testing begins and Honolulu's Rail Project moves onward towards completion!

 

8a61b82d-6b42-46d4-b215-4cddc179ebfa.jpg

 

 



#3 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 20 October 2017 - 08:24 PM

Excerpt:

 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg


 

 

 

HART WEEKLY eBLAST  | October 20, 2017

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 

 

HART TRAIN TESTING PICKS UP THE PACE!

 

The Honolulu Authority for Rapid Transportation and its contractor Ansaldo Honolulu have been turning up the speed in terms of train testing!  Initial tests were conducted at no more than three miles per hour. After successful diagnostics, the speeds were ramped up to 40 miles per hour, with testing at the maximum speed of 55 miles per hours expected soon!

 

b64324a2-ba88-44ba-824b-d588d22ac162.png 

 

The higher speed tests caught the attention of local media who visited HART's Rail Operations Center in Waipahu to get the latest updates.  

 

1008a1ee-e4de-4473-bbcf-e52d0f1d8b35.jpg6c0a04ea-7d26-437a-ab91-c7b43e6f0c42.jpg
 

 

 

 

edc23ff2-bacb-44c2-937a-80633792a06f.jpg35e8e3f4-adf6-47ca-83dc-1ca225f2b49d.jpg
 

 

So far, trains have been testing for about 10 days.  Each time it makes a pass over the energized section in Waipahu, it draws a number of on-lookers hoping to catch a glimpse of Honolulu's Rail Project in action.  The excitement is building!!! 

 

219e47bb-6cec-4591-877f-430f66d114e4.jpg

 



#4 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 30 March 2018 - 05:32 PM

S.gif

3/29/18
 

f09f480a-b4fb-41fe-8d1c-d95511c728b6.jpg

 

Aloha from the 

Honolulu Rail Transit Project!

 

 

HART's Photo of the Week!

 

c08e018e-8faa-4d99-a237-e294fdd2bcf7.png

 
 

 

ON THE MOVE!

219b7823-17ae-4c60-b4e9-58f1e037976d.jpg

S.gif

 

HART and contractor Ansaldo Honolulu Joint Venture continue to test trains on the guideway above Farrington Highway in Waipahu. Engineers put the rail cars through various stress tests to see how they perform and make any needed adjustments.  The trains on hand are expected to undergo tests for the next several months, while more trains arrive to join the fleet. Eventually, the Honolulu Rail Transit Project will operate with twenty, 240-foot trains at its disposal.

 

e83e837b-e6ad-4d25-bfde-9f98f207b98d.png

 

 

Please visit our website at:

www.honolulutransit.org

 

 

d9d1378b-8035-4e60-a29a-3b44b63f97ad.png

 
 
 
 
 

 

 



#5 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 04 April 2018 - 05:29 AM

YouTube:
 

HART Trains Testing over Farrington Hwy

 

Published on Apr 2, 2018
 

HART & Ansaldo Honolulu JV continue train testing on the guideway above Farrington Highway in Waipahu.

 



#6 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 30 June 2019 - 08:02 AM

HART via YouTube

HART Tests Trains Overnight for the First Time

 

Published on Jun 28, 2019

 

 

I wonder why the interior lights are on only on the middle cars; out on the end cars.

-Ross