Central District light rail: Judkins Park Station slated to break ground mid-2017As U-Link light rail moves from weekend novelty to weekday workhorse, Sound Transit is preparing for its next major expansion in the region that will include bringing light rail to the Central District.
http://www.capitolhi...round-mid-2017/
#3
Posted 21 April 2018 - 02:22 PM
Sound Transit:
Project update: April 20, 2018
View of the future Judkins Park Station Platform
Judkins Park Construction Kick-off Open House
As construction begins on the Judkins Park station, we’re sure you have questions about
what’s coming next. Join us on Wednesday, May 2, to meet the contractor and talk with the construction team.
Please join us:
When: Wednesday, May 2, 2018, 5-7 p.m.
Where: Northwest African American Museum
2300 S. Massachusetts St., Seattle, WA 98144
More project info: soundtransit.org/Judkins-Park-Station
New to Sound Transit? Learn more
#4
Posted 02 February 2019 - 08:09 AM
2/1/19:
Project update
Progress continues at Judkins Park Station
Having demolished one of the I-90 bridges crossing Rainier Ave. in October, construction at the Judkins Park Station continues to progress. Check out photos of the latest construction activities.
Stay connected
Watch for future project updates. Forward this to your friends, family, neighbors and people in your community! Encourage them to subscribe.
#5
Posted 15 June 2019 - 07:21 AM
6/13/19
Project update
Judkins Park Station entrances take shape
Over the last few months, the Judkins Park Station has begun to take shape. Crews have formed and poured concrete walls and foundations, while elevator shafts have risen out of the ground. Check out photos of the latest construction activities.
East Link construction more than 50 percent complete
Earlier this spring, the East Link project celebrated a major milestone as construction passed the halfway mark. It will still be a few years before East Link opens and begins operation as the Blue Line but construction continues to make progress.