WMATA news release

 
For immediate release: February 9, 2024

  Metro announces three-year capital construction plans, including Red Line station closures this summer

 

Metro has announced plans for major capital construction over the next three years to modernize the Metrorail system, improve safety and reliability, and maintain a state of good repair. Planned closures are scheduled between summer 2024 and summer 2026, with additional construction planned over the winter holidays.

 

Beginning in early June, Glenmont, Wheaton, Forest Glen, Silver Spring and Takoma stations on the Red Line will be closed. The closure will continue through early September with the possibility of reducing the work zone to allow Takoma Station to reopen prior to the end of construction.

 

The planned work includes upgrading the signaling system, installing communication and train control cables, and repairing the interlocking; which allows trains to cross from one track to the other outside the Takoma Station. Detailed service plans, including free express and local shuttle buses, are being developed and will be announced at least one month prior to the start of the closure.

 

 

2024-Red-Line-Summer-Closure_1.png

 

The work is being planned in coordination with the Maryland Transit Administration Purple Line Project to build a new mezzanine on the platform at Metro’s Silver Spring Station to provide easier access between Metro and the future MTA Purple Line. The Maryland Purple Line light rail line is not part of the Metrorail system, but building the new connection between the two will require the use of both tracks for an extended period and can’t be completed safely and timely with single tracking only.

 

Additional work includes leak mitigation, automatic train control system replacements, traction power cables installation, drain pumping station replacement, tunnel standpipe replacement, and elevator and escalator maintenance.

 

Improvements in planning and scheduling track work through summer, winter, and extended weekend outages instead of extensive single tracking, has also helped reduce the amount of planned service disruptions. In the past seven years, the impact to budgeted service declined by half to just four percent with more weekends free of track work on almost all lines.

 

Following the Red Line closure this summer, major construction is also planned:

 

December 2024 – January 2025

Blue/Orange/Silver Lines Construction Foggy Bottom – GWU to L’Enfant Plaza

Duration: Approximately two weeks

  • Farragut West, McPherson Sq, lower level of Metro Center (upper-level Red Line open), Federal Triangle, Smithsonian stations affected
  • Pour new grout pads and replace fastener replacements to provide smooth, safe rides
  • Includes 6,400 linear feet of grout pad and fastener replacement
  • Installation of 15,000 linear feet fiber optic cable for communication and train control
  • Construction will require isolated closures, but not the full segment between all stations. Developing plans and analysis to close smaller segments and/or single tracking.
  • Alternative to planned work - four months of weekend single tracking, or up to 400 late-night single tracking

Summer 2025

Blue Line  Construction Franconia-Springfield to King Street

Duration: Approximately three weeks

*Exact dates and order of outages to be determined

  • Van Dorn St and Franconia-Springfield stations closed
  • Upgrade train control system
  • Replace worst performing, obsolete signal system
  • System upgrades will bridge to potential next generation signaling system
  • Alternative to planned work – 10 weekend outages and 10 weeks of early weekday closures

Green Lin Construc Congress

Green Line Construction Congress Heights to Branch Avenue
Duration: Approximately six weeks

*Exact dates and order of outages to be determined

  • Southern Ave, Naylor Road, Suitland, and Branch Ave stations closed
  • Install 52,000 linear feet of radio and ancillary fiber optic cable for communication and train control system
  • Required modernization project to improve communications and address FTA findings
  • Repair elevated tracks and bridge
  • Alternative to planned work - seven months of consecutive weekend outages

*All work will be completed before Labor Day with no construction Jul. 4

 

Winter 2025 – Winter 2026

Green/Yellow Lines Construction L’Enfant Plaza to Fort Totten

*Exact dates and duration to be determined

  • Replace grout pad and fasteners
  • Install fiber optic cable for communication and train control system
  • Replace running rail and repair restraining rail
  • Install signals along tracks to support train control system upgrades
  • Stations served by 82 percent more trains than the system average
  • Developing construction plans to optimize service which may include smaller closures, single tracking, or combination of both

Summer 2026

Red Line Construction Friendship Heights to Grosvenor-Strathmo

*Exact dates and duration to be determined

  • Medical Center and Bethesda stations closed
  • Construction to connect Maryland’s MDOT MTA Purple Line with the Bethesda Metrorail Station
  • MDOT MTA Purple Line currently scheduled to begin operating mid-2027


#2 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82873 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 10 February 2024 - 10:51 AM

WTTG-TV, Fox-5 in Washington, DC, 2/9/24:

 


 

 

     5 Red Line Metro stations shut down for summer construction 

 

 

 

Five stations on the east end of Metro’s Red Line will shut down this summer for work to connect the Purple Line light-rail project to the system at Silver Spring.

 

Story



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#3 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43770 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 18 May 2024 - 03:34 PM

WTOP-FM, Washington, DC 4/23/24

 
Metro unveils plan to dampen impact of summer Red Line work that will shut down 5 stations

Metro says free shuttle buses traveling in special bus-only lanes through parts of Montgomery County, Maryland, will help riders affected by the shutdown of five Red Line stations this summer.

 

The Glenmont, Wheaton, Forest Glen and Silver Spring stations will be closed from June 1 through Aug. 31. The Takoma station will be closed from June 1 through June 29.

 

To help riders get around, Metro will roll out four free shuttle routes during the entire closure.  . . .

 

 

Continue here