BART Rebuilding Work affects 3 lines over Labor Day Weekend


  • Please log in to reply
4 replies to this topic

#1 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 19 August 2017 - 12:52 PM

BART news release, 8/14/17:

 

Rebuilding work to impact Warm Springs, Dublin, Oakland Airport lines Labor Day Weekend

 

Downtown%20Oakland%20Labor%20Day%20closu

.pdf of map

 

 

BART crews will be rebuilding trackway in downtown Oakland during Labor Day weekend from the end of service on Friday through Monday, to make the system safer, quieter, and more reliable. No trains will run between 19th Street and Fruitvale stations or between West Oakland and Fruitvale stations and Lake Merritt station will be closed. Riders on the Warm Springs/So. Fremont, Dublin/Pleasanton, and Oakland Airport lines will be impacted (see map on reverse). BART crews cannot complete these critical trackway repairs during the overnight hours when we are normally closed for maintenance, which is why we require this extra time. 

 

Crews will replace rail and upgrade electrical systems. We will also use the time during the closure to do other vital maintenance and repair work.

 

Lake Merritt Station will be closed: AC Transit will provide bus service on its local 18 (to downtown) and 1 bus routes (to Fruitvale) to and from the station. That service will be free for customers who show their BART Ticket. Extra buses will be provided for trips between Lake Merritt and Fruitvale Station. You can expect 10-25 additional minutes of travel time.

 

Fleet of free buses between Fruitvale and 19th Street Stations provided by AC Transit
We will have a fleet of free buses waiting for you outside the station during our normal service hours for “show up and go” service. Just to be safe, please budget an extra 20 to 40 minutes for your trip (especially to OAK airport).

There will be extra staff in our stations to assist you. Follow signs and listen to announcements for important information.

 

Richmond Line
The Richmond line is running all weekend, which means more frequent service between the East Bay, San Francisco, and the peninsula.

 

Travel tips

  • Consider using a station not affected by the bus bridge if you are able, like West Oakland or MacArthur.
  • The Quickplanner is schedule-based--check RealTime for more accurate information.
  • During the closure, the destination signs on platforms in the system from Millbrae and SFO through San Francisco will read "ALL EASTBAY" to prevent passengers from waiting for direct trains to Fremont or Dublin/Pleasanton.
  • Lock your bike at our stations rather than bringing them on crowded buses.
  • If you are travelling from Dublin/Pleasanton or Warm Springs/So. Fremont and want to go to a destination along the lines to the West Bay, Richmond, or Pittsburg Bay Point, you will have to transfer to the bus at Fruitvale and then board a train at 19th Street to reach your destination.
  • If you are coming from the West Bay, West Oakland, Richmond, or Pittsburg/Bay Point and want to go to a destination along the lines to Dublin/Pleasanton or Warm Springs/So. Fremont, you will have to take a train to 19th Street, transfer to a bus and then board a train at Fruitvale reach your destination.

 



#2 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 19 August 2017 - 12:57 PM

Progressive Railroading, 8/16/17:

 
BART preps track work in Oakland
031317-Bay-Area-Rapid-Transit-train.jpg
Crews will replace rail and upgrade electrical systems along a portion of BART's network in Oakland. Photo – BART

 

Bay Area Rapid Transit (BART) crews will rebuild track in downtown Oakland, California, over the Labor Day weekend.

Workers will replace rail and upgrade electrical systems, and perform other maintenance and repair work, BART officials said in a press release.

BART will suspend service on a portion of its lines for the first weekend in September so that crews can complete the work.

 

Continue here.



#3 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82315 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 02 September 2017 - 02:15 PM

BART website:

 


 

 

Rebuilding work to impact Warm Springs, Dublin, Oakland Airport lines Labor Day Weekend

 

 

BART crews will be rebuilding trackway in downtown Oakland during Labor Day weekend from the end of service on Friday through Monday, to make the system safer, quieter, and more reliable. No trains will run between 19th Street and Fruitvale stations or between West Oakland and Fruitvale stations and Lake Merritt station will be closed. Riders on the Warm Springs/So. Fremont, Dublin/Pleasanton, and Oakland Airport lines will be impacted (see map on reverse). BART crews cannot complete these critical trackway repairs during the overnight hours when we are normally closed for maintenance, which is why we require this extra time. 

 

 

Continue



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#4 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82315 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 02 September 2017 - 02:33 PM

E-mail from Capitol Corridor:

 

 


 

 

BART Track Closures in Oakland Over Labor Day Weekend

 

BART will be rebuilding trackway in downtown Oakland during the Labor Day Weekend. No trains will run between the 19th Street and Fruitvale BART stations or between the West Oakland and BART Fruitvale stations. The Lake Merritt BART station will also be closed.

 

Capitol Corridor passengers connecting to BART at the Richmond Station traveling to San Francisco or other stops along that line will be unaffected.

 

Capitol Corridor passengers who connect to BART at Coliseum traveling to San Francisco will be affected. For travel to San Francisco, passengers can connect to the Capitol Corridor/Amtrak bus at the Emeryville Station, which provides service to bus stops downtown San Francisco, or they can take the Capitol Corridor to Richmond and transfer to BART at that station.

 

This work is part of BART’s efforts to rebuild the system to make it safer and more reliable and to reduce traffic. Read more details and see a map of the closure on the BART website.



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#5 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 13 September 2017 - 06:25 PM

news-from-bart_crop.png

Release Date: 9/13/2017

 

Measure RR Update: Labor Day Work Roundup

 

capture_crop.png

 

We've been busy in the ten months since the passage of Measure RR, from prioritizing projects to putting boots on the ground.

 

This video shows how our workers spent the Labor Day weekend, rebuilding major sections of the critical infrastructure that gets you around the Bay Area every day.

 

Click here to explore a list of all the active projects on which we're working.

 

 