Posted 16 July 2023 - 10:40 AM

DCist, 7/14/23:
 


 

    Purple Line Opening Expected To Be Delayed Again, Now Slated For 2027 

 

 

The Purple Line, an upcoming 16-mile light rail line from New Carrollton to Bethesda that has faced multiple delays, is expected to be delayed again till Spring 2027.

 

More



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#112 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82315 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 28 September 2023 - 01:39 PM

Montgomery County 360,   9/26/23:

 


 

    Purple Line construction creating major damage to MoCo roads, officials say  

 

 

While the Purple Line light rail is expected to be completed around 2027, Montgomery County officials say they don’t want to wait that long for repairs to the roads damaged by the project.

 

Details



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#113 KevinKorell

KevinKorell

    Board Leader

  • Sr. Admin
  • PipPip
  • 82315 posts
  • Gender:Male
  • Location:Lakewood, NJ
  • Interests:Making America TRAIN again!

Posted 04 March 2024 - 12:11 PM

Railway, Track, & Structures, 3/4/24:

 


 

 Maryland Transit Administration And Purple Line Transit Partners Announce Updated Opening Date For Light Rail Line        

 

 

The Maryland Department of Transportation Maryland Transit Administration and Purple Line Transit Partners last week announced they are seeking Board of Public Works approval of a modification to the Purple Line Public-Private Partnership Agreement that extends the contractual deadline for achieving Revenue Service Availability to Winter 2027.

 

Read



Kevin Korell


OTOL Board Leader


Lakewood, NJ


#114 CNJRoss

CNJRoss

    Administrator

  • Admin
  • PipPip
  • 43390 posts
  • Gender:Male
  • Location:Fairfax, VA

Posted 05 March 2024 - 08:44 AM

Maryland Matters, 3/1/24

 

Cost of Purple line increases yet again, completion pushed back

 

The Maryland Transit Administration will seek approval next month for as much as $425 million in “relief payments” related to delays in the Purple Line light rail project.

 

Officials announced the extra payments along with a roughly 234-day delay that will push the line’s completion back from spring of 2027 to December of that year.

 

 

Continue here.  