Trains News Wire
New York comptroller finds half of recommendations for LIRR on M9 contract were not implemented
December 13, 2023
Response to 2022 report reflects commuter railroad’s disagreement with original findings
ALBANY, N.Y. — In a follow-up to a 2022 report, the New York Office of the State Comptroller found the cost of a Long Island Rail Road order for M9 electric multiple-unit railcars manufactured by Kawasaki has continued to increase, while half of the recommendations made by the Comptroller’s office in the original report have not been implemented.
The original report found the initial 92-car order had fallen three years behind schedule, with 62 cars accepted, and was $8.9 million over budget. It found the LIRR contributed to the problem on a number of fronts, a conclusion the LIRR said it “fundamentally disagrees with” [see “Report finds Long Island Rail Road shares blame …,” Trains News Wire, March 29, 2022]. The LIRR had subsequently expanded that order by exercising an option for 110 additional cars.
The follow-up report indicates 172 cars had been accepted as of July of this year, with the rest expected to be accepted by the end of May 2024. It also indicates the budget for the M9 procurement has increased by more than $2.1 million, to $735.7 million, since the initial audit.
Continue here.